Willow House Client (demo) — WRK-PRJ-1001

Willow House, North West · Residential · Detached house. One design record: revision r2 (Frozen) is both the customer's approved system and the engineer's build blueprint.

Demo project data. Network addressing, port allocations, cable IDs and pricing are worked examples generated from the design — confirm every model-specific requirement against the manufacturer integration guide on survey.

Stage
Install
Proposal accepted
Design revision
r2
Frozen · frozen 2026-08-12
Contract value
£30,461
£24/mo managed
Install readiness
Verification needed
25 unverified requirements
Handover
Blocked
1 mandatory test failures

Handover is blocked

A mandatory acceptance test has failed. Resolve and re-test before the handover pack can be signed off and support activated.

Pack is not install-ready — 25 verification blockers

Each item below is unknown until it is confirmed against the manufacturer integration guide on survey. WRK does not invent ports, firewall rules or firmware requirements. Resolve these before first fix begins.

  • Network · WRK Home Controller — WRK cloud relay: Outbound HTTPS only. No inbound rule. Remote support uses the controller's outbound tunnel.
  • Network · Controller to IoT VLAN: Allow Management → IoT for control traffic; deny IoT → Management. Enable mDNS reflection for discovery.
  • Network · Cameras / NVR: No internet egress for cameras by default. NVR viewing from Management only.
  • Network · Vendor cloud integrations (per manufacturer): To verify from manufacturer integration guide
  • Device · WRK WRK Home Controller (Whole site): pairing/adapter requirement unverified
  • Device · WRK 8" Wall Panel (Whole site): pairing/adapter requirement unverified
  • • and 19 more in the Network and Devices tabs

Scope & revision control

Any change after freeze requires a change order and a new design revision; this pack regenerates from that revision.

Pack

epk-prj-1001-r2 · r2

Generated

1970-01-01

Design frozen

2026-08-12

Engineer

M. Rees (Installer)

QA

T. Okafor (QA)

Project manager

L. Bennett (PM)

Prerequisites

  • Design revision frozen and customer accepted
  • Access windows agreed with the site
  • Mains works assigned to a competent qualified installer where required
  • All BOM items received and checked

Access windows

  • Weekdays 08:00–17:00

Dependencies

  • Broadband service live at the comms position
  • Containment routes available for first fix
  • Any items marked 'verify on survey' resolved before ordering

Zones in scope

Kitchen

Kitchen · Wi-Fi Good

lighting, climate, blinds, av, sensors, energy

Living Room

Living Room · Wi-Fi Excellent

lighting, climate, blinds, av, sensors

Hallway

Hallway · Wi-Fi Good

lighting, climate, cctv, access, sensors

Bedroom 2

Bedroom · Wi-Fi Good

lighting, climate, blinds, sensors

Office

Office / Study · Wi-Fi Good

lighting, climate, av

Garden

Garden / External · Wi-Fi Poor

lighting, cctv, access

Garage

Garage · Wi-Fi Patchy

lighting, cctv, energy